G-2001-52
A General Multi-Shift Scheduling System
et référence BibTeX
Rotating work schedules are encountered in several industries and public sector organizations where work is carried out 24 hours a day, seven days a week. This article provides a classification of the main constraint classes governing the design of rotating schedules. A constraint programming algorithm is developed and tested on several real-life examples. Computational results confirm the efficiency and robustness of the proposed approach.
Paru en décembre 2001 , 21 pages
Axe de recherche
Application de recherche
Publication
jan. 2004
A general multi-shift scheduling system
et
Journal of the Operational Research Society, 55(11), 1208–1217, 2004
référence BibTeX