Accelerating Project Schedules Through Task Execution Overlap
et référence BibTeX
Schedule compression is a major concern in project management. We propose an extension of the classical crashing model to include the managerial practice of judiciously violating precedence constraints between normally consecutive activities. The generalized model still allows efficient cost curve and schedule computations.
Paru en juillet 1989 , 17 pages
Ce cahier a été révisé en décembre 1989