Accelerating Project Schedules Through Task Execution Overlap

et

référence BibTeX

Schedule compression is a major concern in project management. We propose an extension of the classical crashing model to include the managerial practice of judiciously violating precedence constraints between normally consecutive activities. The generalized model still allows efficient cost curve and schedule computations.

, 17 pages